Before Adding AI Capacity Make Infrastructure Visible, Comparable and Ready to Optimise

Before Adding AI Capacity: Make Infrastructure Visible, Comparable and Ready to Optimise

Learn how MENA enterprises can plan AI capacity through workload visibility, comparable metrics, rightsizing, optimisation, and evidence-based infrastructure expansion.

AI demand is pushing infrastructure teams toward fast capacity decisions. FinOps Foundation’s 2026 survey (1,192 practitioners, $83B+ in annual technology spend) found that 98% of organisations now manage AI spend, up from 63% in 2025, and many are asked to self-fund AI investments through optimisation savings [1]. At the same time, Flexera’s 2026 State of the Cloud reported that wasted cloud spend rose to 29% for the first time in five years as GenAI adoption increased to 58% [2]. The market signal is clear: adding capacity before understanding utilisation can lock in cost and waste.

The cost of getting the decision wrong is rising. JLL’s 2026 Global Data Center Outlook forecasts average shell-and-core construction costs at $11.3 million per MW in 2026, with AI fit-out adding up to $25 million per MW; in primary markets, average grid-connection waits exceed four years [3]. For operators in the UAE, Saudi Arabia, Qatar and Oman, the practical sequence is evidence-first: make workloads visible, make metrics comparable, optimise the existing estate, then size the remaining gap.

Visibility: see what is actually consuming capacity

Most organisations track facility metrics, but fewer can see workload-level utilisation. Uptime Institute’s 2026 Global Data Center Survey found that 87% of operators track IT/data-centre power and 79% track PUE, while only 37% collect server utilisation data [4]. Without workload-level visibility, capacity requests mix real growth with idle allocation, fragmentation and undocumented constraints.

A usable baseline connects four elements:

  • Workload identity: service, owner, environment, business criticality.
  • Resource footprint: allocated and consumed compute, memory, storage, network, and accelerator resources where measurable.
  • Time profile: average use, peaks, peak duration, batch windows, low-activity periods.
  • Constraints: service levels, dependencies, placement rules, latency, resilience and data-handling limits.

The baseline must cover every environment in scope. Record telemetry gaps as gaps; do not replace them with assumptions. Energy data belongs in the same view: facility consumption and infrastructure telemetry should be read together, with the measurement boundary stated clearly.

Comparability: use one metric language

Visibility becomes decision-grade only when teams compare like with like. FinOps Foundation reports that data-centre teams follow a maturity path: “first gain visibility, then build planning discipline, and only then optimize for value” [1]. The same report identifies the top missing capability as granular monitoring of AI spend (tokens, LLM requests and GPU utilisation), followed by pre-deployment architecture costing and a single pane of glass for technology spend; adoption of FOCUS is growing as a normalisation layer [1].

Konstantin Petrosov, Chief Technology Officer at Usetech, made the same operational point at DECE 2026 in Doha:

“The most crucial part here is to use the same standards for all players. Using the same standards makes it possible to compare workloads and performance metrics.”

Source: panel “The AI Economy: Data Centres, Power & the Cost of Intelligence”, DECE 2026, Doha, 16 November 2026. Lightly edited for clarity. https://usetech.com/news/usetech-at-events-in-doha/

A metric dictionary should define each measure’s unit, scope, formula, sampling interval and reporting window. Teams need to separate allocated from consumed resources, average from peak, and observed demand from reserved headroom. Workloads should be compared within relevant classes: interactive inference, training, data preparation and general enterprise services behave differently.

Optimisation: prove the remaining gap before expansion

Once the baseline is comparable, optimisation should test whether the existing estate can absorb demand. Flexera found that 73% of organisations operate hybrid cloud, but workload placement decisions are slowed by application dependencies (54%), technical feasibility (44%) and on-premises vs cloud cost comparison (43%) [2]. That makes dependency mapping part of optimisation, not a separate exercise.

Practical levers are familiar, but they need measured validation:

  • Rightsizing: reduce over-allocation where observed demand and service requirements allow.
  • Balancing: move workloads where placement constraints permit.
  • Consolidation: remove fragmentation or duplicated environments without weakening isolation.
  • Scheduling: shift flexible batch/training work away from constrained periods.

Market telemetry shows why this step matters. Cast AI’s 2026 report, based on ~23,000 Kubernetes clusters, observed average GPU utilisation of 5%, CPU 8% and memory 20%, with CPU overprovisioning rising to 69% year-on-year; automated rightsizing cut provisioned CPU footprint by ~50% and reduced OOM kills from 40–50 per interval to near zero [6]. This telemetry comes from Kubernetes clusters and should not be read as a universal data-centre benchmark; it illustrates the allocation-consumption gap in that environment.

Every optimisation scenario needs an owner, service-impact check, acceptance metric and rollback path. After validated changes, the baseline should be updated; only then should the remaining capacity gap be priced.

Local conditions: UAE, Saudi Arabia, Qatar, Oman

The measurement sequence is common, but implementation boundaries are local: where workloads run, who operates them, which service obligations apply, and which power or regulatory constraints shape expansion.

Saudi Arabia is a current example. As of 13 November 2026, SEEC’s draft Technical Regulation on Energy Efficiency Standards and Requirements for Data Centers (design IT load ≥15 MW) was under public consultation on Istitlaa until 3 December 2026 [7]. Because it is a draft, the useful action is preparation, not legal interpretation: organise workload inventories, utilisation history, measurement boundaries, energy/resource data and documented controls. Legal and compliance teams should interpret final requirements.

Decision checklist

Before approving AI capacity expansion, decision-makers should be able to answer:

  • Which workloads and services create the demand, and what is their measured peak and average profile?
  • Are allocation, consumption, utilisation, peak and headroom defined consistently across all environments in scope?
  • Which dependencies, service levels and resilience constraints limit change?
  • Which rightsizing, balancing, consolidation or scheduling scenarios were tested, with what service impact and rollback?
  • What quantified gap remains after optimisation, and what evidence shows expansion is the right response?

AI capacity planning is stronger when every expansion request can be traced from workload demand to measured use, tested optimisation and a quantified residual gap.

If you want to apply this sequence to your own environment, you can request an infrastructure visibility and utilisation assessment from Usetech.

Sources

[1] FinOps Foundation, State of FinOps 2026. https://data.finops.org. 

[2] Flexera, 2026 State of the Cloud Report / blog summary. https://www.flexera.com/blog/finops/flexera-2026-state-of-the-cloud-report-the-convergence-of-cloud-and-value. https://www.jll.com/en-us/insights/market-outlook/data-center-outlook. 

[3] Uptime Institute, 16th Annual 2026 Global Data Center Survey press release and executive summary. https://uptimeinstitute.com/about-ui/press-releases/16th-annual-2026-global-data-center-survey-deployment-of-high-density-racks-rising-fast-operators-face-continued-recruiting-and-retention-pressures. 

[4] Panel “The AI Economy: Data Centres, Power & the Cost of Intelligence”, DECE 2026, Doha, 16 November 2026. https://usetech.com/news/usetech-at-events-in-doha/

[5] Cast AI, 2026 State of Kubernetes Optimization Report. https://cast.ai/reports/kubernetes-optimization-report. 

[6] Saudi Energy Efficiency Center (SEEC), draft Technical Regulation on Energy Efficiency Standards and Requirements for Data Centers, public consultation via Istitlaa. https://istitlaa.ncc.gov.sa/ar/Energy/seec/TechnicalRegulation.

Portrait of Ekaterina Samsonova
Ekaterina Samsonova
Head of PR and Marketing MENA at Usetech
15+ years in B2B/IT marketing, PR, and external communications across MENA, Europe, and Russia

Let’s work with us.

Tell us more about your request by leaving the application in the contact form below, and our team will contact you.

Contact us.

Our team is ready to assist you – just drop us a message or connect with one of our offices below.

Tech for business.

Monthly newsletter with main insights and trends.